Soluna Holdings Inc.SLNHBusiness update
Soluna Finishes Kati 1 and Secures Conditional Base Load Position for All 166 MW in ERCOT
Soluna energized the final 14 MW at Project Kati 1, bringing total operating capacity to about 206 MW, and ERCOT conditionally classified the full 166 MW Kati campus as Base Load.
Summary written with AI from the company's SEC filing. How we summarize
How SLNH reacted
2 trading sessions- Move
- +3.3%
- Volume
- 1.2×
- vs 20-day avg
- 20 sessions on
- −12.5%
- vs prior close
Aug 10, 2026filingOct 6, 2026
Close $1.20 on Sep 4, 2026 → $1.24 on Sep 9, 2026. The window covers the filing day and the next session because releases can come out before, during or after market hours. Prices are split-adjusted; other news can move the stock too.
Key points
- Soluna energized the final 14 MW at Project Kati 1, completing the 83 MW site.
- Total operating capacity increases to approximately 206 MW.
- ERCOT conditionally classified the full 166 MW Kati campus as Base Load in its Batch Zero process.
- The classification is conditional pending ERCOT's verification, under which a project may be removed if the applicant does not respond to information requests.
- The Company says every phase of Project Kati 1 was delivered on time, with infrastructure costs on budget.
By the numbers
- Total operating capacity
- approximately 206 MW
- Project Kati 1 site capacity
- 83 MW
- Full Kati campus, conditional Base Load
- 166 MW
- Final Kati 1 energization
- 14 MW
- Development pipeline
- approximately 6.3 GW
- AI and HPC capacity in development
- more than 650 MW
As stated in the release. Check the original for definitions and periods.
From the release
Soluna Holdings, Inc. (“Soluna” or the “Company”) (NASDAQ: SLNH), a developer of green data centers for intensive computing applications, including AI and Bitcoin mining, today announced two milestones at its Project Kati campus in Willacy County, Texas. The Company has energized the final 14 MW at Project Kati 1, completing the 83 MW site, and has been notified that ERCOT has conditionally classified the full 166 MW Kati campus, including the planned Kati 2 AI expansion, as Base Load in its Batch Zero interconnection process.
“This is proof that the Soluna model works. We build where the power already is and we bring generation with us, and ERCOT’s framework recognizes exactly that.”
Investor questions
0 answered so farQuestions this release raises. We wrote them from the release text; they haven't been answered by Soluna Holdings Inc. yet. Pick one or write your own; we send the most-asked to its investor relations team and publish answers here for everyone.
What does the conditional Base Load classification under ERCOT's Batch Zero mean for the 166 MW campus until verification is completed?
How does the approximately 206 MW total operating capacity break down between Kati 1 and the company's other operating capacity?
How do the 48 MW Galaxy Digital fill and the 35 MW remaining phase relate to the 83 MW Kati 1 total, and what is Bitdeer's co-mining role?
Ask SLNH a question
SLNH release history
All 38Business update
Soluna and Bitdeer Expand Agreement to 35 MW at Project Kati 1Business update
Soluna Secures Conditional Base Load Position for Project Dorothy's 100 MW in ERCOT Batch ZeroInvestor event
Soluna to Participate in the H.C. Wainwright 28th Annual Global Investment ConferenceBusiness update
Soluna Finishes Kati 1 and Secures Conditional Base Load Position for All 166 MW in ERCOT (this release)
Business update
Soluna and Bitdeer Enter 28 MW Agreement at Project Kati 1Business update
Soluna Closes Purchase of 397 Acres for Project Dorothy 3Earnings
Soluna Reports Q2'26 Results; Revenue Grows 145% Year-Over-Year
Filing details
- Form
- 8-K, press release as Exhibit 99
- Filed
- September 8, 2026
- Accession no.
- 0001493152-26-041699
- 8-K items
- 7.01 Regulation FD disclosure
- 9.01 Financial statements and exhibits
- Company
- Soluna Holdings Inc. · Nasdaq: SLNH · Albany, NY
After the Release is independent; companies don't pay for coverage. Headlines and excerpts come from filings on SEC EDGAR, and summaries are AI-assisted. Read the original for full details. Nothing here is investment advice. Report an error.