Soluna Secures Conditional Base Load Position for Project Dorothy's 100 MW in ERCOT Batch Zero

ERCOT conditionally classified the 100 MW Project Dorothy campus as Base Load in Batch Zero; Soluna has also submitted a load interconnection request for an additional 50 MW at the site.

Summary written with AI from the company's SEC filing. How we summarize

How SLNH reacted

2 trading sessions
Move
−5.0%
Volume
0.6×
vs 20-day avg
20 sessions on
−28.6%
vs prior close

Aug 14, 2026filingOct 12, 2026

Close $1.19 on Sep 11, 2026 → $1.13 on Sep 15, 2026. The window covers the filing day and the next session because releases can come out before, during or after market hours. Prices are split-adjusted; other news can move the stock too.

Key points

  • ERCOT has conditionally classified the 100 MW Project Dorothy campus in Texas as Base Load in Batch Zero.
  • The classification follows a conditional Base Load position for the full 166 MW at Project Kati the prior week.
  • Soluna submitted a load interconnection request for an additional 50 MW at Dorothy, which ERCOT is studying directly.
  • The classification is conditional pending ERCOT’s verification process; Soluna expects ERCOT to confirm it.
  • Total operating capacity is approximately 206 MW, with a development pipeline of approximately 6.3 GW.

By the numbers

Project Dorothy conditional Base Load
100 MW
Project Kati conditional Base Load
166 MW
Combined conditional Base Load, Texas campuses
266 megawatts
Additional load request at Dorothy
50 MW
Total operating capacity
approximately 206 MW
Development pipeline
approximately 6.3 GW

As stated in the release. Check the original for definitions and periods.

What's next

  1. Not specified

    ERCOT confirmation of the conditional Base Load classification for Project Dorothy

  2. Not specified

    ERCOT study of the additional 50 MW load request at the Dorothy site

Dates are the company's own and may change. Follow SLNH to hear when they happen.

From the release

Soluna Holdings, Inc. (“Soluna” or the “Company”) (NASDAQ: SLNH), a developer of green data centers for intensive computing applications, including AI and Bitcoin mining, today announced that ERCOT has conditionally classified its 100 MW Project Dorothy campus as Base Load in Batch Zero. The classification follows last week’s conditional Base Load position for the full 166 MW at Project Kati.

“We put the load at the generation instead of waiting years in an interconnection queue. Dorothy has run that way from the start.”
John Belizaire, CEO
Continue reading on SEC EDGAR

Investor questions

0 answered so far

Questions this release raises. We wrote them from the release text; they haven't been answered by Soluna Holdings Inc. yet. Pick one or write your own; we send the most-asked to its investor relations team and publish answers here for everyone.

  • How does Base Load classification preserve Project Dorothy's interconnection capacity compared with the queue process the release describes?

  • Which ERCOT verification information requests must Soluna answer to keep Project Dorothy in Batch Zero, as the release's removal condition describes?

  • How do Dorothy 1 and 2's 98 MW of energized capacity reconcile with the 100 MW Dorothy campus and the approximately 206 MW total operating capacity cited?

Ask SLNH a question

We review every question before publishing it, and send the most-asked to the company's investor relations team. We don't publish promotion, abuse or requests for non-public information.

0/600

SLNH release history

All 38
  1. M&A

    Soluna Agrees to Form Strategic Partnership with Applied Digital to Develop Wind-Powered AI Data Center in Texas
  2. Shareholder / governance

    Soluna Elects Dan Golding to Board of Directors
  3. Business update

    Soluna and Bitdeer Expand Agreement to 35 MW at Project Kati 1
  4. Business update

    Soluna Secures Conditional Base Load Position for Project Dorothy's 100 MW in ERCOT Batch Zero (this release)

  5. Investor event

    Soluna to Participate in the H.C. Wainwright 28th Annual Global Investment Conference
  6. Business update

    Soluna Finishes Kati 1 and Secures Conditional Base Load Position for All 166 MW in ERCOT
  7. Business update

    Soluna and Bitdeer Enter 28 MW Agreement at Project Kati 1

Filing details

Form
8-K, press release as Exhibit 99
Filed
September 14, 2026
Accession no.
0001493152-26-042479
8-K items
Company
Soluna Holdings Inc. · Nasdaq: SLNH · Albany, NY

After the Release is independent; companies don't pay for coverage. Headlines and excerpts come from filings on SEC EDGAR, and summaries are AI-assisted. Read the original for full details. Nothing here is investment advice. Report an error.